| HOME > PROJECTS > COMPRESSOR & PUMP STNS. |
![]() |
| Client: Project: Description: |
EnCana Ladyfern Field, NE British Columbia Two (2) 3,300 BHP compressor packages with Waukesha 12UAT27GL engines driving Ariel JGC/4 compressors, 70 MMSCFD flow each, 7,000 kPa to 11,200 kPa. |
![]() |
![]() |
Client: Project: Description: |
Morrison Petroleum Bulrush Gathering & Processing Facility Project 25 MMSCFD sour gas gathering system and sour gas compression processing facility. System included amine treating and glycol dehydration for fuel gas, power generation and utilities. Pipeline system of about 30 miles of 3”, 4” and 6”. |
|
![]() |
Client: Project: Description: |
Husky Energy Inc. Moose Mtn. Alberta Installation of two 1,400 BHP Compressor Packages. |
|
![]() |
Client: Project: Description: |
Husky Energy Inc. Maclean Creek Alberta Installation of two 1,400 BHP Compressor Packages. |
|
![]() |
Client: Project: Description: |
BP Canada Cochin Pipeline Pump Stations Provided detail design, procurement and project management of the addition of two 2,000 HP pump stations on the Cochin Pipeline. Products handled include ethane, ethylene, propane, butane and NGL. |
|
![]() |
Client: Project: Description: |
Apache Canada Ltd. Consort Alberta Project management, engineering, design, drafting, permitting for a 3,000 BPD Sour Oil Treating Facility including a 10,000 BPD water treating / pumping disposal facility. |
|
![]() |
Client: Project: Description: |
Talisman Energy Inc. Provost Alberta Project Management, detailed design, engineering, drafting, permitting for the installation of a 1,500 BPD Sour Oil Battery including a 8,000 BPD water treating / pumping disposal facility. |
|